Mahar Hall Projects

Program Studies
Completed Projects
Minor Rehab12.2014
Replace Windows10.2007
Enhanced Maintenance & Restoration11.2003
Rehab HVAC02.2002
Replace Plaza/Repair Below Plaza Spaces08.2001
Smart Classrooms09.2000
Replace Exterior Doors09.1998
Repair Elevator06.1997
Improve Handicap Doors/Ramps01.1996
Rehabilitate Steam Traps - Mechanical Rooms04.1995
Asbestos Abatement/Steam Line Replacement06.1992
Install Electric & Steam Meters04.1992
Replace Roof10.1991
Air Monitoring/Inspection For Project 1014408.1991
Install Gas Fired Water Heaters04.1990
Installation Of Energy Management System06.1988
Repair/Replace Entrance Doors 12.1986
Repair/Replace Heating Coils-HVAC Units02.1986
Provide Energy-Efficient Air Dampers07.1984
Repair Condensate Return Line12.1975
Social Science Building04.1967